Project, programme and portfolio: the differences according to ISO 21506
A project is a temporary undertaking with set objectives, a programme a group of interdependent undertakings with a shared benefit, and a portfolio the whole set of strategically managed undertakings. ISO 21506:2024 defines the three terms in clauses 3.61, 3.54 and 3.46. What matters is what belongs together and how success is measured.
In brief
The three terms describe three levels at which organizations group and manage undertakings. The table sets out the main characteristics side by side.
| Characteristic | Project | Programme | Portfolio |
|---|---|---|---|
| Entry in ISO 21506:2024 | 3.61 | 3.54 | 3.46 |
| Purpose | achieve set objectives within a limited time | generate an overarching benefit from several results | align an organization's undertakings with its strategy |
| Components | work packages and deliverables | programme components (3.56): projects, subsidiary programmes, other work | portfolio components (3.47): projects, programmes, subsidiary portfolios, other work |
| Relationship between the parts | one shared result | interdependent in content | not required; competition for the same resources |
| Time frame | clearly limited | limited, but often several years and less sharply defined | no fixed duration, regular review |
| Control | project management (3.65) | programme management (3.57) | portfolio management (3.48) |
| Key question | Is the undertaking being delivered well? | Does the benefit arise from the interplay? | Are these the right undertakings? |
Project
ISO 21506 describes a project by two characteristics: it pursues one or more set objectives, and it is limited in time. Other definitions, for example in the German standard DIN 69901, also mention the uniqueness of the conditions, limited resources and a separate, temporary organization.
What mainly separates a project from day-to-day business is its planned end. An end date can move. An undertaking without a planned end, however, is an ongoing task. If a sequence of activities recurs regularly, it is more likely to be called a process.
A project is managed through project management. It clarifies objectives and scope, plans schedules, costs and resources, and takes corrective steps when the work deviates from the plan. In detail: Project in the PMDecoder glossary.
Programme
A programme groups undertakings that do not lead to the desired result on their own. Only their coordinated interplay generates the intended benefit. ISO 21506 calls these building blocks programme components. They include projects, subsidiary programmes and other work such as training or the transition into operations.
Programmes usually pursue a strategic objective and often run for several years. Their composition is flexible. Components are added, adjusted or dropped if the benefit can be achieved better in another way.
Programme management sets the sequence and interfaces and shifts resources between the components. It is judged less by individual projects finishing on time than by the benefit actually realized. In detail: Programme in the PMDecoder glossary.
Portfolio
A portfolio groups undertakings so that an organization can view, compare and manage them together. Its parts are called portfolio components. These can be projects, programmes, subsidiary portfolios and other work such as feasibility studies.
Unlike in a programme, the components need not be related in content. They belong together because they compete for the same budgets and specialists and are meant to contribute jointly to the strategy. Larger organizations often maintain an overall portfolio with sub-portfolios for each business unit.
Portfolio management decides which undertakings are started, continued, deferred or terminated. It therefore does not ask how an undertaking is delivered well, but whether it is the right one. In detail: Portfolio in the PMDecoder glossary.
Common confusions
- Large project instead of programme: An extensive project with many subprojects remains a project as long as it delivers a single result. A programme only arises when several independently managed undertakings jointly generate a benefit.
- Programme instead of portfolio: Anyone who calls all the undertakings of a unit a "programme", although they run independently of one another, is actually describing a portfolio.
- Portfolio and portfolio management: The portfolio is the set of undertakings; portfolio management is the activity of managing them. The same applies to programme and programme management.
- "Project portfolio": This term is widely used in German (Projektportfolio). According to ISO 21506, however, a portfolio contains not only projects but also programmes and other work.
- Everyday language: Funding schemes or packages of measures are often called a "programme" without being managed as a programme in the project management sense.
- Day-to-day business in the portfolio: Ongoing operations are generally not a portfolio component, even if they draw on the same resources.
Practical example
Fictitious example for illustration. A manufacturer of household appliances wants to significantly reduce the energy consumption of its plants.
- Project: The compressed air system in plant A is replaced. Objective, budget and completion date are fixed. The project ends with the acceptance of the new system.
- Programme: The replacement of the compressed air system, a photovoltaic installation, energy monitoring and training for shift supervisors together form a programme. No component alone reduces consumption to the intended extent. The programme management measures success by energy consumption per appliance produced.
- Portfolio: In the company's portfolio, the energy programme sits alongside product developments, new sales software and a market study. A committee of the executive management reviews all components twice a year. Because specialists are scarce, it defers the sales software by six months.
The same undertaking can therefore be a project, a programme component and, through the programme, part of the portfolio at the same time.
Equivalents in other frameworks
The PMI PMBOK Guide has equivalent terms for all three concepts. The same applies to the associated management disciplines:
- Project: Project; project management: Project management
- Programme: Program; programme management: Program management
- Portfolio: Portfolio; portfolio management: Portfolio management
No equivalents are currently recorded for programme component and portfolio component. Further mappings are shown in the concordance; all terms of the standard with detailed entries are in the PMDecoder glossary.
Terms covered
- ProjectUndertaking with a start and an end that is meant to reach set objectives, usually with limited resources and its own organization.
- ProgrammeGroup of related projects and other work that are steered together in order to achieve an overarching benefit.
- PortfolioCollection of projects, programmes and other work that an organization steers jointly in order to put its strategy into practice.
- Programme componentProject, subordinate programme or other work that forms part of a programme and contributes to its benefits.
- Portfolio componentProject, programme, subordinate portfolio or other work that is managed as part of a portfolio.
- Project managementPlanning, organizing, controlling and closing projects so that their objectives are achieved in terms of time, cost and quality.
- Programme managementCoordinated steering of several related projects that are together meant to achieve an overarching benefit.
- Portfolio managementSelection, prioritization and ongoing control of all of an organization's projects and programmes with a view to its strategy.
Sources
More topics
- Output, outcome and benefit: what an undertaking really achievesDelivered, used, gained: how output, outcome and benefit differ according to ISO 21506.
- Governance and management: who sets the framework and who managesSetting the framework or managing the work: how governance, governing body, project governance and project management fit together.
- Corrective action and preventive action: after and beforeWhy ISO 21506 defines corrective and preventive action twice each, and what separates the two.