The terms of ISO 21506:2024

ISO 21506:2024 defines 97 terms in 100 entries. The list shows them in the order of the standard, with the English term from the standard and a short explanation in our own words. Each term is linked to a detailed entry in the PMDecoder glossary.

iso21506.com editorial team · A service of iso21500.de; subject-matter responsibility: Dennis Hain. Who is behind this site

Updated:

Terms by clause number

The explanations are our own texts and do not reproduce the wording of the standard. Only the text of the standard is authoritative. The search covers the terms and the explanations.

Terms from ISO 21506:2024, clause 3, in the order of the standard
No. Term Explanation in our own words
3.1 100 % rule Principle for work breakdown structures: the elements directly below an element together cover exactly all of its work, no more and no less. In detail on PMDecoder: 100 % rule
3.2 Activity Defined piece of work without which a project, programme or portfolio cannot be finished; in the schedule it has a duration, start and finish. In detail on PMDecoder: Activity
3.3 Actual cost Costs actually incurred for the project work carried out up to a cut-off date. In detail on PMDecoder: Actual cost
3.4 Baseline Approved version of a plan for scope, schedule or cost against which actual project progress is measured. In detail on PMDecoder: Baseline
3.5 Basis of estimate Record of the data, assumptions and methods on which an estimate of what the planned activities will need is based. In detail on PMDecoder: Basis of estimate
3.6 Benefit Positive effect that an undertaking actually brings about for an organization or its stakeholders, such as savings, better quality or new opportunities. In detail on PMDecoder: Benefit
3.7 Budget at completion Approved total budget for completing all the work of an activity, work package, control account, project or programme. In detail on PMDecoder: Budget at completion
3.8 Business case Justification of an undertaking that weighs benefits, costs, risks and alternatives and shows why the investment is worthwhile. In detail on PMDecoder: Business case
3.9 Change register Continuously maintained overview of all changes raised in a project or programme, with their key details and current status. In detail on PMDecoder: Change register
3.10 Change request Proposal, submitted in writing, to change a project or programme, stating reasons and effects and put forward for a decision. In detail on PMDecoder: Change request
3.11 Communication plan Overview that sets out who in the project receives or supplies which information, when, how often and through which channel. In detail on PMDecoder: Communication plan
3.12 Configuration management Managing the components, versions and characteristics of a project result so that it is always clear which version applies. In detail on PMDecoder: Configuration management
3.13 Control Ongoing comparison of the project's status with the plan and initiation of action when variances put the objectives at risk. In detail on PMDecoder: Control
3.14 Control account Point at which the work content, schedule, budget and actual costs of one part of a project come together and are owned jointly. In detail on PMDecoder: Control account
3.15 · 3.16 Corrective action Action that remedies a variance that has already occurred; in quality management, removing the cause of a defect so that it does not recur. In detail on PMDecoder: Corrective action
3.17 Cost variance Difference between the value of the work performed and the actual cost incurred for it; a negative value means more expensive than planned. In detail on PMDecoder: Cost variance
3.18 Critical path Sequence of activities in the network schedule without float whose total duration determines the earliest finish of a project or phase. In detail on PMDecoder: Critical path
3.19 Decomposition Step-by-step refinement of an undertaking into smaller parts that are easier to plan and control, repeated as more detail becomes known. In detail on PMDecoder: Decomposition
3.20 Deliverable Verifiable result that is produced in a project and handed over to the client, users or subsequent work. In detail on PMDecoder: Deliverable
3.21 Earned value Monetary value of the work actually finished by a cut-off date, measured with the budget that was planned for that work. In detail on PMDecoder: Earned value
3.22 Earned value management Method for judging how far and how efficiently a project or programme has progressed by combining scope, schedule, budget and actual cost. In detail on PMDecoder: Earned value management
3.23 Earned value management planning Preparatory planning that sets out how a project builds its measurement of performance: baseline, crediting rules, responsibilities and reports. In detail on PMDecoder: Earned value management planning
3.24 Earned value measurements Figures from which the earned value of a project or programme is derived and interpreted for control purposes. In detail on PMDecoder: Earned value measurements
3.25 Estimate at completion Forecast of the total cost a project, a programme or part of one will have incurred once all its work is finished, based on the current position. In detail on PMDecoder: Estimate at completion
3.26 Estimate to complete Expected cost of all the work still outstanding at the cut-off date, for example in a project or a single work package. In detail on PMDecoder: Estimate to complete
3.27 Governance Framework of principles, rules and responsibilities that determines how an organization is steered and overseen. In detail on PMDecoder: Governance
3.28 Governing body Top-level person or body, such as a board, that is ultimately answerable for how an organization or group of organizations is governed. In detail on PMDecoder: Governing body
3.29 Hierarchical decomposition Top-down breakdown of the scope of a project or programme, level by level, until manageable elements of the work breakdown structure emerge. In detail on PMDecoder: Hierarchical decomposition
3.30 Integrated baseline review Joint review by client and project team of whether the performance measurement baseline is complete, realistic and understood alike by all. In detail on PMDecoder: Integrated baseline review
3.31 Issue Problem or unresolved question that has already arisen in a project and must be dealt with and decided so that work can continue. In detail on PMDecoder: Issue
3.32 Issue register Document in which all issues of a project or programme are recorded together with actions, owners and status. In detail on PMDecoder: Issue register
3.33 Lead Negative time offset on a dependency that allows a successor to start or finish earlier than the link would otherwise permit. In detail on PMDecoder: Lead
3.34 Lessons learned Experience from a project, programme or portfolio, captured as knowledge intended to make future undertakings better. In detail on PMDecoder: Lessons learned
3.35 Management information system Hardware and software that gathers data from projects and programmes and turns it into analyses and reports for decision-makers. In detail on PMDecoder: Management information system
3.36 Management reserve Portion of the budget held back for unforeseeable work within the agreed scope, released by management and not part of the measurement baseline. In detail on PMDecoder: Management reserve
3.37 Milestone Significant point in time for a project, a programme or a portfolio, such as a decision or handover date, already scheduled or still to be fixed. In detail on PMDecoder: Milestone
3.38 Network schedule Graphical representation of a project's activities and their dependencies as a network of nodes and connecting arrows. In detail on PMDecoder: Network schedule
3.39 Opportunity Uncertain event or circumstance that, if it occurs, would have a positive effect on a project's objectives. In detail on PMDecoder: Opportunity
3.40 Organizational breakdown structure Hierarchical representation of the organizational units that manage a project or programme and perform its work, including partners. In detail on PMDecoder: Organizational breakdown structure
3.41 Outcome Change in an organization or its environment that comes about once the result delivered by an undertaking is put to use. In detail on PMDecoder: Outcome
3.42 Output What a project or programme ultimately delivers: all its deliverables taken together, whether objects, documents or services. In detail on PMDecoder: Output
3.43 Parent element Element of a work breakdown structure whose work has been split into at least two elements on the level below. In detail on PMDecoder: Parent element
3.44 Performance measurement baseline Measurement basis of earned value management: the plan of work and budget spread over time, leaving out the management reserve held back. In detail on PMDecoder: Performance measurement baseline
3.45 Planned value Budgeted value of the work that, according to the baseline, should have been completed by a given cut-off date. In detail on PMDecoder: Planned value
3.46 Portfolio Collection of projects, programmes and other work that an organization steers jointly in order to put its strategy into practice. In detail on PMDecoder: Portfolio
3.47 Portfolio component Project, programme, subordinate portfolio or other work that is managed as part of a portfolio. In detail on PMDecoder: Portfolio component
3.48 Portfolio management Selection, prioritization and ongoing control of all of an organization's projects and programmes with a view to its strategy. In detail on PMDecoder: Portfolio management
3.49 Portfolio manager Person appointed to a portfolio who answers for it contributing to the organization's strategic objectives. In detail on PMDecoder: Portfolio manager
3.50 Portfolio plan Core document of a portfolio: which strategic objectives it pursues, which components belong to it and which plans it is steered by. In detail on PMDecoder: Portfolio plan
3.51 · 3.52 Preventive action Action that removes the cause of a possible variance or defect before it occurs. In detail on PMDecoder: Preventive action
3.53 Product breakdown structure Hierarchical breakdown of a project's result into its sub-products and components. In detail on PMDecoder: Product breakdown structure
3.54 Programme Group of related projects and other work that are steered together in order to achieve an overarching benefit. In detail on PMDecoder: Programme
3.55 Programme benefit Measurable change brought about by a programme that its stakeholders regard as a gain and that moves its objectives forward. In detail on PMDecoder: Programme benefit
3.56 Programme component Project, subordinate programme or other work that forms part of a programme and contributes to its benefits. In detail on PMDecoder: Programme component
3.57 Programme management Coordinated steering of several related projects that are together meant to achieve an overarching benefit. In detail on PMDecoder: Programme management
3.58 Programme manager Person appointed to a programme who answers for the intended benefits and deliverables being achieved. In detail on PMDecoder: Programme manager
3.59 Programme plan Binding core document of a programme that brings the technical requirements and control plans of all components together into one whole. In detail on PMDecoder: Programme plan
3.60 Progress report Regular, brief report on the current state of a project covering progress, variances, risks and the decisions needed. In detail on PMDecoder: Progress report
3.61 Project Undertaking with a start and an end that is meant to reach set objectives, usually with limited resources and its own organization. In detail on PMDecoder: Project
3.62 Project assurance Independent, planned review of a project that gives the sponsor and the commissioning organization a reliable view of whether it is on course. In detail on PMDecoder: Project assurance
3.63 Project governance Framework of responsibilities, rules and decision paths that determines who approves a project, who steers it and to whom it is answerable. In detail on PMDecoder: Project governance
3.64 Project life cycle Sequence of phases that a project passes through from initiation to closure. In detail on PMDecoder: Project life cycle
3.65 Project management Planning, organizing, controlling and closing projects so that their objectives are achieved in terms of time, cost and quality. In detail on PMDecoder: Project management
3.66 Project management office Function or organizational unit that makes managing projects easier, for example through methods, support and an overview for senior management. In detail on PMDecoder: Project management office
3.67 Project manager Person or position that plans and steers a project on behalf of the client and brings it to completion, with responsibility for its results. In detail on PMDecoder: Project manager
3.68 Project plan Under ISO 21506, the binding document that brings together a project's technical baselines and its management baselines. In detail on PMDecoder: Project plan
3.69 Project scope The work released for a project together with its results, delimited from everything that is explicitly excluded. In detail on PMDecoder: Project scope
3.70 Quality assurance Part of quality management that builds confidence, through planned and verified ways of working, that quality requirements will be met. In detail on PMDecoder: Quality assurance
3.71 Quality control Part of quality management that checks work results, identifies deviations from requirements and initiates their correction. In detail on PMDecoder: Quality control
3.72 Residual risk Risk that remains once the agreed response actions have been carried out, assessed by likelihood and impact. In detail on PMDecoder: Residual risk
3.73 Resource loading Determining which people, equipment, materials and other means the planned work of an undertaking needs, and when. In detail on PMDecoder: Resource loading
3.74 Resource breakdown structure Hierarchical breakdown of the resources needed in a project by type, such as staff by qualification, equipment and materials. In detail on PMDecoder: Resource breakdown structure
3.75 Responsibility assignment matrix Table that records, for each task or result, which role is accountable, carries it out, contributes or is kept informed. In detail on PMDecoder: Responsibility assignment matrix
3.76 Risk Possible event that is still uncertain, possibly made up of several events, and that could benefit or harm an undertaking. In detail on PMDecoder: Risk
3.77 Risk assurance Review activities intended to give sponsors reliable evidence that a project or programme can still justify its investment despite its risks. In detail on PMDecoder: Risk assurance
3.78 Risk breakdown structure Hierarchical breakdown of the threats and opportunities of a project or programme, usually arranged by source of risk. In detail on PMDecoder: Risk breakdown structure
3.79 Risk contingency reserve Time or budget allowance planned for identified risks, to be used only if they materialize. In detail on PMDecoder: Risk contingency reserve
3.80 Risk response Defined and documented action taken in relation to an identified risk, ranging from prevention to recovery after the event. In detail on PMDecoder: Risk response
3.81 Risk tolerance Limit up to which a project may carry a risk; once the limit is crossed, a defined response has to follow. In detail on PMDecoder: Risk tolerance
3.82 Rolling wave planning Planning approach in which near-term stages are planned in detail and later ones only roughly, with detail added step by step. In detail on PMDecoder: Rolling wave planning
3.83 Schedule buffer Reserve of time deliberately placed at chosen points in the schedule so that unexpected delays are cushioned before they hit key dates. In detail on PMDecoder: Schedule buffer
3.84 Schedule performance index Ratio of earned value to planned value; values below one indicate that the project is behind plan. In detail on PMDecoder: Schedule performance index
3.85 Sponsor Senior manager who backs a project within the organization, secures resources and takes decisions on fundamental issues. In detail on PMDecoder: Sponsor
3.86 Stakeholder Anyone with an interest in an undertaking such as a project, who can influence it or considers themselves affected by it, whether person, group or organization. In detail on PMDecoder: Stakeholder
3.87 Strategic alignment State in which the undertakings in a portfolio, through selection and ongoing adjustment, actually serve an organization's strategy. In detail on PMDecoder: Strategic alignment
3.88 Task order Document by which specific services are actually ordered on the basis of a contract that is already in place. In detail on PMDecoder: Task order
3.89 Technical performance Measure of which required functions or capabilities a result has already reached while the work is still under way. In detail on PMDecoder: Technical performance
3.90 Threat Possible event that, if it occurs, would impair schedule, cost, quality or other project objectives. In detail on PMDecoder: Threat
3.91 Time-phased budget Budget assigned to the periods or phases in which the work is expected to take place and the costs to arise. In detail on PMDecoder: Time-phased budget
3.92 Undistributed budget Budget released for approved work that for the time being has not yet been allocated to any control account. In detail on PMDecoder: Undistributed budget
3.93 Variance Gap between the approved baseline and what has actually been achieved, for example in schedule, cost or scope. In detail on PMDecoder: Variance
3.94 Variance at completion Budget at completion minus estimate at completion; shows how far the total cost is expected to depart from the plan. In detail on PMDecoder: Variance at completion
3.95 Variance threshold Limit for variances, set in advance, that determines when the project manager or the sponsor has to step in. In detail on PMDecoder: Variance threshold
3.96 Work breakdown structure Hierarchical decomposition of the entire project scope into ever smaller components, down to the work package. In detail on PMDecoder: Work breakdown structure
3.97 Work breakdown structure dictionary Companion document to the work breakdown structure that records, element by element, content, results, responsibility and other details. In detail on PMDecoder: Work breakdown structure dictionary
3.98 Work breakdown structure element Any individual building block of the work breakdown structure at a particular level, from the top element down to the work package. In detail on PMDecoder: Work breakdown structure element
3.99 · 3.100 Work package Defined unit of related activities at the lowest level of the work breakdown structure, with its own result, timeframe and budget. In detail on PMDecoder: Work package
Embed a term on your site

Copy the HTML code to show the short explanation with its source on your website, intranet or course materials.

<blockquote cite="https://iso21506.com/en/terms/#t-3-1" style="border-left:3px solid #173d6b;margin:0;padding:.5em 1em">
  <p><strong>100 % rule</strong> – Principle for work breakdown structures: the elements directly below an element together cover exactly all of its work, no more and no less.</p>
  <footer>Source: <a href="https://iso21506.com/en/terms/#t-3-1">iso21506.com</a> · ISO 21506:2024, 3.1</footer>
</blockquote>

Notes on use

  • Terms: The standard is available only in English and French. The terms on this page are the English terms of the standard. The German and Spanish versions of this site use editorial translations; where no established equivalent exists, they keep the English term, for example business case, governance, lessons learned, outcome and output.
  • Citing: Refer to the standard with its edition and clause, for example “ISO 21506:2024, 3.21”. For the explanations on this site, please cite iso21506.com as the source.
  • Equivalents: The concordance shows what the terms are called in the PMBOK Guide, PRINCE2, IPMA ICB, PM² or Scrum.