Term comparison

Governance and management: who sets the framework and who manages

Governance determines who in an organization may decide what and to whom they are accountable for it; management acts within this framework. ISO 21506:2024 defines governance (3.27), governing body (3.28), project governance (3.63) and project management (3.65). Project governance applies the framework to the individual project, and project management manages the work within it.

iso21506.com editorial team · A service of iso21500.de; subject-matter responsibility: Dennis Hain. Who is behind this site

Updated:

In brief

Governance and management sit at different levels. The table shows how the terms from ISO 21506 are distributed.

CharacteristicGovernanceProject governanceProject management
Entry in ISO 21506:20243.273.633.65
Objectthe organization or part of ita single projecta single project
Key questionWho may decide what, under which rules?Who authorizes and directs the project, and to whom is it accountable?How does the project achieve its objectives?
Typical contentprinciples, policies, bodies, oversightroles, decision points, escalation, reporting linesplanning, organizing, monitoring, corrective steps
Whogoverning body (3.28), such as the executive board or supervisory boardsponsor, steering committee, project manager in their rolesproject manager and project team

Governance and governing body

Governance is the regulatory framework of an organization. It determines who makes which decisions, under which rules this happens and to whom account must be given. It includes values and principles, binding policies, bodies with defined powers, and procedures for oversight and reporting.

For projects, programmes and portfolios, governance is the outer framework. It determines how undertakings are approved, overseen and closed.

The governing body is responsible for this framework. Depending on legal form and size, it is a single person, such as an owner, or a body such as an executive board, management board or supervisory board. A business unit or a group of several organizations can also have its own governing body. In detail: Governance and Governing body in the PMDecoder glossary.

Project governance

Project governance applies the organization's framework to a single undertaking. It determines who approves the project, who commissions and directs it, which decision is made at which level and when matters are escalated.

Typical building blocks are the roles of sponsor, steering committee and project manager, decision points between phases, and rules for changes and terminations. An independent project assurance function can be added to show the sponsor whether the project is on track.

Small undertakings can often manage with the organization's standard rules. Large or risky projects are given their own, more detailed governance. In detail: Project governance in the PMDecoder glossary.

Project management

Project management comprises the leadership tasks, methods and tools that carry a project from initiation to closure. It clarifies objectives and scope, plans schedules, costs and resources, organizes collaboration and takes corrective steps when deviations occur.

The term refers both to the activity and to the position or group that performs it. It must be distinguished from the specialist project work: whoever programs a piece of software does project work; whoever manages the schedule, budget and coordination for it does project management. In detail: Project management in the PMDecoder glossary.

Common confusions

  • Governance as management: Management acts within the framework; governance sets and oversees it. Anyone who mixes the two ends up overseeing themselves.
  • Governance as compliance: Compliance with laws and internal rules is part of governance, not the whole of it.
  • Governing body and steering committee: A steering committee directs a single project or programme on behalf of the organization. The governing body is responsible for the governance of the whole organization.
  • Governing body and top management: In small organizations the two often coincide. In larger ones, top management runs day-to-day business while the governing body is answerable for governance.
  • Project organization and project governance: The project organization describes the structure of the project. Project governance additionally regulates decision-making and accountability paths.

Practical example

Fictitious example for illustration. A regional energy supplier introduces a new billing system.

  • Governance: The supervisory board, as the governing body, has stipulated that undertakings above two million euros are only approved with a reviewed business case. Each of these undertakings needs a sponsor from the executive management, and the supervisory board receives a report every six months.
  • Project governance: For the billing project, the commercial managing director takes on the role of sponsor and chairs the steering committee. The committee decides on changes above 15 person-days; the project manager decides on smaller ones.
  • Project management: The project manager plans the migration of customer data, coordinates the business department and the software vendor, and reports monthly to the committee. When a test fails, she moves two work packages within her own scope of authority.

Equivalents in other frameworks

No equivalent is currently recorded for governing body. Further mappings are shown in the concordance. Guidance on the governance of projects, programmes and portfolios is given in ISO 21505, see ISO 21500 series.