Corrective action and preventive action: after and before

A corrective action responds to a variance that has already occurred; a preventive action prevents a possible one. ISO 21506:2024 defines each term twice, in 3.15 and 3.16 and in 3.51 and 3.52. The reason is two contexts: the control of work and quality management.

iso21506.com editorial team · A service of iso21500.de; subject-matter responsibility: Dennis Hain. Who is behind this site

Updated:

In brief

The core of the distinction is timing: after the problem or before it. The table summarizes both contexts.

CharacteristicCorrective actionPreventive action
Entries in ISO 21506:20243.15 and 3.163.51 and 3.52
Triggeridentified variance or a defect that has occurredpossible variance or possible defect
In the control of workbrings the ongoing work back in line with the planadjusts future work so that no variance arises
In quality managementeliminates the cause of a defect that has occurred so that it does not recureliminates the cause of a possible defect before it occurs
Typical occasionsexceeded variance threshold, audit finding, complaintlessons learned, risk analyses, trends in indicators, defects elsewhere
Effectiveness is shown whenthe variance disappears and does not recurthe problem does not occur in the first place

Why there are two entries each

ISO 21506 arranges its entries alphabetically by the English term. Three terms appear twice, each for a different context. Two of them are corrective action and preventive action. This explains why the vocabulary standard contains 100 entries but only 97 terms.

The double definition reflects two ways of thinking that meet in projects. One context is the control of projects and programmes: it is about performance, schedules and costs compared with the plan. The other is quality management: it is about defects and their causes. Anyone using the term should therefore make clear which context is meant. The exact wording is contained only in the standard itself.

Corrective action

A corrective action comes into play when a variance has already been identified. In the control of work, it redirects ongoing activities so that performance matches the plan again. Examples are additional staff, a changed sequence of work or a renegotiated delivery date.

In quality management, corrective action goes deeper. It eliminates the cause of a defect so that it does not recur. This distinguishes it from a mere correction, which only fixes the individual defect.

The project manager decides on corrective actions within their authority. If they affect agreed objectives, the client decides. A variance threshold sets in advance the point at which intervention is required. In detail: Corrective action in the PMDecoder glossary.

Preventive action

A preventive action takes effect before a problem arises. In the control of work, future work is adjusted so that no variance from the plan occurs in the first place. In the handling of defects, the cause of a possible defect or other undesirable situation is eliminated.

Triggers are often lessons learned from earlier undertakings, identified risks, trends in indicators or defects that have already occurred elsewhere. Typical measures are additional inspection steps, training, a second supplier or early clarification of unclear requirements.

Prevention does not always pay off. Its effort should be proportionate to the probability and impact of the problem avoided. In detail: Preventive action in the PMDecoder glossary.

Common confusions

  • Correction and corrective action: Reworking a defective part is a correction. Only eliminating the cause is a corrective action in the quality sense.
  • Corrective action and contingency measure: A contingency measure is planned in advance for the case that a known risk occurs. A corrective action is only determined after a variance has been identified.
  • Prevention and risk response: In risk management, preventive action corresponds to reducing or avoiding a risk. Risk response is broader and extends to recovery after a risk has occurred.
  • Control and quality control: Control compares the project status with the plan. Quality control checks work results against requirements. Both can trigger corrective actions, but in different senses.

Practical example

Fictitious example for illustration. A municipality builds a primary school in two construction phases.

  • Corrective action in control: The shell construction work is three weeks behind plan and exceeds the agreed variance threshold. The project manager brings in a second crew and brings forward the interior fit-out in completed areas.
  • Correction and corrective action in the quality sense: At acceptance, several window joints are leaking. They are resealed; that is the correction. The cause turns out to be a missing installation specification. The site management adds it and introduces an interim inspection; that is the corrective action.
  • Preventive action: For the second construction phase, the municipality first has a sample window installed and accepted. Only then does series installation begin. The experience feeds into the lessons learned for future construction projects.