ISO 21506 and other frameworks: the concordance

For 73 of the 97 terms in ISO 21506:2024, other frameworks have terms with the same or a closely related meaning. The concordance shows them side by side, for example what “earned value” is called in the PMBOK Guide or which PRINCE2 term corresponds to the sponsor.

iso21506.com editorial team · A service of iso21500.de; subject-matter responsibility: Dennis Hain. Who is behind this site

Updated:

What the concordance is for

Many organizations work with several approaches at the same time: the project management handbook is based on the ISO 21500 series, staff are certified according to PMI or PRINCE2, and development teams work with Scrum. The concordance helps to align documents and roles between these worlds.

Terms that sound the same do not always mean the same. Whether an equivalent matches exactly or is only similar is described in the relevant entry in the PMDecoder glossary.

Equivalents by topic

The rating comes from the PMDecoder glossary: equivalent, closely related, partially overlapping or false friend (sounds the same but means something else).

Project, programme, portfolio and governance

Equivalents to ISO 21506:2024 – Project, programme, portfolio and governance
No.ISO 21506Equivalents in other frameworks
3.6 Benefit
3.8 Business case
3.10 Change request
3.27 Governance
3.34 Lessons learned
3.37 Milestone
3.41 Outcome
  • PMI / PMBOK Guide Outcomeequivalent
3.42 Output
  • PMI / PMBOK Guide Outputclosely related
3.46 Portfolio
3.48 Portfolio management
3.49 Portfolio manager
3.50 Portfolio plan
3.54 Programme
  • PMI / PMBOK Guide Programequivalent
3.57 Programme management
3.58 Programme manager
3.59 Programme plan
3.61 Project
  • PMI / PMBOK Guide Projectequivalent
3.62 Project assurance
3.63 Project governance
3.64 Project life cycle
3.65 Project management
3.66 Project management office
3.67 Project manager
3.76 Risk
  • PMI / PMBOK Guide Riskequivalent
3.85 Sponsor
3.86 Stakeholder
3.96 Work breakdown structure
3.99 · 3.100 Work package

Planning, structure and sequencing

Equivalents to ISO 21506:2024 – Planning, structure and sequencing
No.ISO 21506Equivalents in other frameworks
3.2 Activity
3.4 Baseline
3.11 Communication plan
3.18 Critical path
3.19 Decomposition
3.20 Deliverable
3.33 Lead
  • PMI / PMBOK Guide Leadequivalent
3.38 Network schedule
3.40 Organizational breakdown structure
3.53 Product breakdown structure
3.68 Project plan
3.69 Project scope
3.74 Resource breakdown structure
3.75 Responsibility assignment matrix
3.82 Rolling wave planning
3.97 Work breakdown structure dictionary

Control, change and quality

Equivalents to ISO 21506:2024 – Control, change and quality
No.ISO 21506Equivalents in other frameworks
3.12 Configuration management
3.13 Control
3.15 · 3.16 Corrective action
3.31 Issue
  • PMI / PMBOK Guide Issueequivalent
3.32 Issue register
3.51 · 3.52 Preventive action
3.60 Progress report
3.93 Variance
3.95 Variance threshold

Earned value management and budget

Equivalents to ISO 21506:2024 – Earned value management and budget
No.ISO 21506Equivalents in other frameworks
3.3 Actual cost
3.7 Budget at completion
3.14 Control account
3.17 Cost variance
3.21 Earned value
3.22 Earned value management
3.25 Estimate at completion
3.26 Estimate to complete
3.36 Management reserve
3.44 Performance measurement baseline
3.45 Planned value
3.84 Schedule performance index
3.94 Variance at completion

Risks and reserves

Equivalents to ISO 21506:2024 – Risks and reserves
No.ISO 21506Equivalents in other frameworks
3.39 Opportunity
3.72 Residual risk
3.78 Risk breakdown structure
3.79 Risk contingency reserve
3.80 Risk response
3.81 Risk tolerance
3.90 Threat
  • PMI / PMBOK Guide Threatequivalent

How the mappings are made

The basis is the PMDecoder glossary. There, each term is assigned to a concept; terms from different frameworks with the same concept appear here as equivalents. The mappings are editorial drafts and are undergoing expert review.