Tools
Earned value calculator
Enter budget at completion, planned value, earned value and actual cost; the calculator shows cost and schedule variance, CPI, SPI and the forecasts EAC, ETC and VAC at once. It runs in your browser only and sends no data.
Calculator
| Results | Formula | |
|---|---|---|
| Cost variance (CV) 3.17 | EV − AC | – |
| Schedule variance (SV) | EV − PV | – |
| Cost performance index (CPI) | EV ÷ AC | – |
| Schedule performance index (SPI) 3.84 | EV ÷ PV | – |
| Estimate at completion (EAC) 3.25 | BAC ÷ CPI | – |
| Estimate to complete (ETC) 3.26 | EAC − AC | – |
| Variance at completion (VAC) 3.94 | BAC − EAC | – |
| To-complete performance index (TCPI) | (BAC − EV) ÷ (BAC − AC) | – |
How to read the values
- Indices above 1 are good: a CPI of 1.10 means every euro spent delivered work worth 1.10 euros; an SPI of 0.90 means 10 per cent less work is done than planned.
- Variances above 0 are good: a positive cost variance means the work done cost less than planned.
- EAC assumes here that the cost efficiency so far continues (BAC ÷ CPI). In practice there are other variants, for example with a new estimate for the remaining work.
- TCPI shows the cost efficiency the remaining work would need for the budget to hold. Values well above 1 are rarely achievable.
Terms from ISO 21506
Budget at completion (3.7), planned value (3.45), earned value (3.21), actual cost (3.3), cost variance (3.17), schedule performance index (3.84), estimate at completion (3.25), estimate to complete (3.26) and variance at completion (3.94) are defined in ISO 21506:2024. Our explanations are in the list of terms. Guidance on earned value management itself is given in ISO 21508 and ISO 21512 (ISO 21500 series).